HE Peruća


(Peruća Hydro Power Plant)
Banski prolaz 1, 21230 Sinj
tel: ++ 385 21 70 78 00,
fax: ++ 385 21 70 79 80

 

Director: Josip Macan

General data:

  • location: area of Split-Dalmatia County on the Cetina River
  • type: adjacent to dam with a reservoir
  • in-service year: 1960
  • refurbishment start: 2002
  • refurbishment completion: 2008
  • total capacity: 60 MW
  • Unit A: 30 MW (in service in 2005)
  • Unit B: 30 MW (in service in 2007)

Energy data:

  • installed flow: Qi = 120 m3/s (2x60)
  • design head: Ht = 47 m
  • maximum head: Hmax=56.5 m
  • turbine capacity at design head: 24.7 MW
  • turbine capacity at max head: 61.4 MW (30.7 + 30.7 MW)
  • maximum annual production: (1974-2010) Emax = 166 GWh (2010)
annual production 2010 2011 2012 2013 2014
electricity

203
GWh

86
GWh
56
GWh
179
GWh
176
GWh

Unit type year of
construction
A 30 MW Francis turbine
Q i = 60 m3 /s H n = 56.5 m, Pi=30,7 MW
2005
Synchronous generator
Sn = 34 MVA Un = 10.5 kV cos f = 0.8
B 30 MW Francis turbine
Q i = 60 m3 /s H n = 56.5 m, Pi=30,7 MW
2007
Synchronous generator
Sn = 34 MVA Un = 10.5 kV cos f = 0.8


 